Virtual Testing: engineering test specifications
Led discovery, scope, iterative delivery, stakeholder alignment, and feedback through maintenance/support transition.
Evidence snapshot: CV maintained 30 September 2026
- Problem
- Engineers needed to retrieve historical test reports and use their evidence to support test-specification work.
- Contribution
- Led an MVP for report retrieval, evidence summarization, specification verification, and generation assistance, with continued governance and access work identified for regional handover.
- Design decision
- The delivered scope was bounded to approximately 1,000 historical DGBB/SXC reports rather than claiming company-wide coverage.
- Outcome and evidence
- One user reported saving 2–3 hours on one benchmark-data retrieval task. This is individual early feedback, not an average or audited productivity measure.
Source: public CV online or dated CV (PDF). No private project documents are linked.